Wednesday, 14 May 2014

PMI-002 Real Exam Questions

Vendor Name: PMI
 

Exam code: PMI-002
 

Exam Name: Certified Associate in Project Management (CAPM)
 

Click the link below to get full version
http://www.certifyguide.com/exam/PMI-002/

http://www.certifyguide.com/exam/PMI-002/

Question: 1

 
A contract cannot contain _____________.

A. Illegal activities
B. deadline for the completion of the work
C. Penalties and fines for disclosure of intellectual rights
D. Al1 of the above

Answer: A    

Question: 2
 
Which one of the following comes first in the project plan?

A. Scope Statement
B. Quality Plan
C. WBS
D. Development Plan

Answer: A    

Question: 3
 
You are project manager of a project. During the process of selecting the sellers, you reject one vendor because it doesn't have the manufacturing capability. This is an example of which selection tool?

A. Weighting system
B. Screening system
C. Seller rating system
D. Expert judgment

Answer: B    

Question: 4
 
______________ provides details about how the project scope may be changed.

A. Control Scope system
B. VeiirV Scope
C. Scope Charter
D. Scope Management plan

Answer: D    

Question: 5
 
Which of the following technique to identify the underlying cause of a problem and take steps to prevent further occurrence?

A. Root cause analysis
B. Quality audits
C. Project audits
D. Risk audits

Answer: A    

Question: 6
 
Which of the following provides the least accurate in estimating?

A. Rough order of magnitude
B. Budget estimate
C. WBS estimate
D. Definitive estimate

Answer: A    

Question: 7
 
Who has the responsibility for informing the final deliverable to all stakeholders?

A. Project Manager
B. Sponsor
C. Team Lead
D. Management

Answer: A    

Question: 8
 
What is a corrective action?

A. An action that brings future project events Into alignment with the project plan
B. An action to correct something in the project
C. An action to prevent something in the project
D. Corrective action is not related to project

Answer: A    

Question: 9
 
Assumptions are factors that, for planning purposes, are considered to be ______.

A. True, real, or certain
B. True, real, or uncertain
C. Real
D. Verbal

Answer: A    

Question: 10
 
A complete set of indexed project records is called __________.

A. Project archives
B. Index
C. sow
D. Project History

Answer: A    

Question: 11
 
You are managing a project that will implement a new Insurance software package. Two project team members have difficulty working together. They come to you, for help resolving the issues. You immediately set up a meeting that includes the functional manager. After the meeting you and the functional manager discuss the issues and agree on a solution. What type of organizational structure you are working in?

A. Functional
B. Balanced matrix
C. Piojectized
D. Strong Matrix

Answer: B    

Question: 12
 
You have been with the organization; you constantly hear rumours about a certain CAPM failing to live up to the CAPM Code. What you should do?

A. You can gather as much information as you can before proceeding
B. Confront the person immediately
C. Ignore the rumours
D. ^ass the rumours along

Answer: A    

Question: 13
 
Who is responsible for issuing the project charter?

A. The project manager
B. The project sponsor
C. The Team lead
D. The nianagement

Answer: B    

Question: 14
 
In PMBOK, the seller is ________ to the project team.

A. Internal
B. External
C. Outside
D. Assigned

Answer: B    

Question: 15
 
Project Quality Management includes:

A. Customer satisfaction
B. Prevention over inspection
C. Continuous improvement
D. Al1 of the above

Answer: D    

Question: 16
 
You are the project manager of the MKTG Project. The project has a budget of $200,000 and is expected to last 2 years. The project is now 20 percent complete and is on schedule. What is the BAC?

A. $-00,000
B. $200,00
C. $50,000
D. None of the above

Answer: A    

Question: 17
 
A Risk Register is a part of the ________.

A. Project Scope Statement
B. Project Management plan
C. Project Scheduling plan
D. Project Charter

Answer: B    

Question: 18
 
A Risk Register is a part of the ________.

A. Administrative Closeout
B. Contract Closeout
C. Not closed
D. Al1 of the above

Answer: D

Question: 19
 
Which type of network diagram is also referred to activity-on-arrow (AOA) diagrams?

A. Precedence Diagramming Method (PDM)
B. Gant Cnart Diagram (GCD)
C. Dependency Diagramming Method (DDM)
D. Arrow Diagramming Method (ADM)

Answer: D    

Question: 20
 
Create Procurement document is done in _______.

A. Plan Procurements
B. Conduct Procurements
C. Administer Procurements
D. Close Procurements

Answer: A    

Question: 21
 
Cost benefit analysis, scorecard modelling, payback periods, and internal rate of return are examples of ____________.

A. Enterprise benefits measurement methods when selecting a project
B. Integral parts of the SOW
C. Ways to ensure stakeholder commitment
D. Project selection methods

Answer: A    

Question: 22
 
Most change requests are a result of _______.

A. Value added change (enhancements)
B. Schedule constraints
C. Regulatory constraints
D. Improvement to the project scope

Answer: A    

Question: 23
 
Based on the PMBOK, who is ultimately responsible for the project quality?

A. Project team
B. Project manager
C. QA manager
D. Validation engineer

Answer: B    

Question: 24
 
The end of the project comes after which of the following?

A. Project charter
B. F'na' deliverable
C. Schedule
D. QA activities are done

Answer: B    

Question: 25
 
The product description of a project can help to create procurement details. Which one of the following best describes product description?

A. The product description defines the contracted work, based on the requirements of the project customer
B. The product description defines the contracted work
C. The product description defines the requirements for the contract work
D. Al1 of the above

Answer: A    

Question: 26
 
During the planning phase of your project, your project team members have discovered another way to complete a portion of the project scope. This method is safer for the project team, but may cost more for the customer. This is an example of _______.

A. Alternative identification
B. "'s^ assessment
C. Alternative selection
D. Product analysis

Answer: A    

Question: 27
 
What is the lowest level in a work breakdown structure?

A. Project task
B. w°rl< package
C. sow
D. None

Answer: B    

Question: 28
 
Administrative Closure should occur ___________.

A. At the end of each phase of the project
B. At the end of the whole project
C. At the end of 50% of the project
D. At the end of 100% of the project

Answer: A    

Question: 29
 
In which phase project manager is assigned to a project?

A. During the initiation stage
B. During the planning stage
C. After approval of budget
D. After the project is proven feasible

Answer: A    

Question: 30
 
Who gives project acceptance?

A. Sponsor
B. Customer
C. Project Manager
D. Team Lead

Answer: B    

http://www.certifyguide.com/exam/PMI-002/

Vendor Name: PMI
 

Exam code: PMI-002
 

Exam Name: Certified Associate in Project Management (CAPM)
 

Click the link below to get full version

http://www.certifyguide.com/exam/PMI-002/

No comments:

Post a Comment