Question: 1

 
Identify the missing word(s) from the following sentence. A project is a temporary organization that is created for the purpose of delivering one or more business products according to an agreed?

A. Senior User
B. Business Case
C. Change
D. Cost

Answer: B   

Question: 2
 
According to PRINCE2, which of the following is a characteristic of a project compared to that of business operations?

A. Incurs cost
B. Introduces business change
C. Delivers benefits
D. Creates products

Answer: B   

Question: 3
 
Which of the following is FALSE?

A. Manage risks is a PRINCE2 principle
B. Manage by exception is a PRINCE2 principle
C. Focus on products is a PRINCE2 principle
D. Tailor to suit the project environment is a PRINCE2 principle

Answer: A   

Question: 4
 
According to PRINCE2, which of the following are the aspects of project performance to be managed?

A. Processes, themes, principles
B. Time, cost, quality, people
C. Time, cost, quality
D. Time, cost, quality, scope, benefits, risk

Answer: D   

Question: 5
 
What environment does PRINCE2 assume?

A. Third party
B. Customer/Supplier
C. Fixed-price contract
D. Management and Specialist

Answer: B   

Question: 6
 
A characteristic of a project is that they come with an element of uncertainty. Which of the following PRINCE2 themes will help with the identification and management of such uncertainty?

A. Quality
B. Risk
C. Change
D. Organization

Answer: B   

Question: 7
 
Which is a benefit of using PRINCE2?

A. Stakeholders are kept out of planning and decision making
B. Participants understand each other's roles and needs
C. Stakeholders are not involved in assuring the project work
D. All problems are escalated to all stakeholders

Answer: A   

Question: 8
 
Which PRINCE2 principle supports planning only to a level of detail that is manageable and foreseeable?

A. Continued business justification
B. Manage by exception
C. Focus on products
D. Manage by stages

Answer: D   

Question: 9
 
Which is NOT a PRINCE2 integrated element?

A. The principles
B. The techniques
C. The themes
D. Tailoring PRINCE2 to the project environment

Answer: B   

Question: 10
 
Which is a characteristic of a project?

A. Are risk free
B. Have no uncertainty
C. Are managed as part of business as usual
D. Are cross-functional

Answer: D   

Question: 11
 
Which is one of the six aspects of project performance that needs to be managed?

A. Issues
B. People
C. Benefit
D. Tolerance

Answer: C   

Question: 12
 
Identify the missing words in the following sentence... A principle of PRINCE2 is that a project has defined and agreed?

A. Roles and responsibilities
B. Specialist teams with appropriate technical skills
C. Management jobs with job descriptions
D. Senior managers at all levels of the project management team

Answer: A   

Question: 13
 
Identify the missing words in the following sentence... A PRINCE2 project is and controlled on a stage-by-stage basis?

A. Planned, monitored
B. Developed, reported
C. Designed, assigned
D. Planned, produced

Answer: A   

Question: 14
 
Identify the missing word in the following sentence... A PRINCE2 project has defined for each project objective to establish limits of delegated authority?

A. Allowances
B. Tolerances
C. Roles
D. Deviations

Answer: B   

Question: 15
 
Identify the missing word in the following sentence... A PRINCE2 project focuses on the definition and delivery of, in particular their quality requirements?

A. Benefits
B. Products
C. Activities
D. Outcomes

Answer: B   

Question: 16
 
Which of the following is a TRUE principle of a PRINCE2 project?

A. Please refer to section 2.3 in the PRINCE2 Manual
B. Work Package level activities are identified during Starting up a Project
C. A project has defined and agreed roles and responsibilities
D. Every project will need a different project management approach

Answer: B   

Question: 17
 
Identify the missing words in the following sentence... A Project is a that is created for the purpose of delivering one or more business products according to an agreed Business Case?

A. Temporary organization
B. Skilled environment
C. One-off Endeavour
D. Unique team of stakeholders

Answer: A   

Question: 18
 
Which of the following statements is TRUE?

A. PRINCE2's focus is on engaging with the business stakeholders only
B. PRINCE2 does not seek to engage with any stakeholders outside of the project environment
C. PRINCE2 is based on a customer/supplier environment
D. PRINCE2 assumes the supplier will specify the desired result and probably pay for the project

Answer: B   

Question: 19
 
Which of the following statements is FALSE? PRINCE2 provides projects with . . .

A. The explicit recognition of project responsibilities
B. A thorough but economical structure of reports
C. Regular progress meetings throughout the project
D. Plans designed to meet the needs of the different levels in the management team

Answer: C   

Question: 20
 
Which of the following does PRINCE2 recognize as being project characteristics?
1. Projects are the means by which we introduce business change
2. Projects have a defined start and end
3. No project is unique
4. Projects often cross the normal functional divisions within an organization

A. 1, 2, 3
B. 1, 2, 4
C. 1, 3, 4
D. 2, 3, 4

Answer: B   

Question: 21
 
The PRINCE2 principle 'continued business justification' states that a requirement for a project is that... There is justifiable reason to start the project and justification should remain valid throughout the life of the project. Which one of the following does PRINCE2 also state for this principle?

A. The Business Case will include details of all project risks
B. A product must deliver tangible, financial benefits
C. Clear ownership of the Business Case is documented
D. The justification is documented and approved

Answer: D   

Question: 22
 
Which of the following PRINCE2 elements are described as being the aspects of project management that must be addressed continually and in parallel throughout the project?

A. The Principles
B. The Processes
C. The Themes
D. Tailoring PRINCE2 to the project environment

Answer: C   

Question: 23
 
Which of the following PRINCE2 elements are described as being the guiding obligations and good practices which determine whether the project is being managed using PRINCE2?

A. The Principles
B. The Processes
C. The Themes
D. Tailoring PRINCE2 to the project environment

Answer: A   

Question: 24
 
Which of the following are the integrated elements which make up the structure of PRINCE2?

A. Principles, Themes, Processes, Tailoring to the project environment
B. Outputs, Outcomes, Benefits
C. Organization, Plans, Progress, Business Case, Risk, Quality, Change
D. Time, Cost, Quality, Scope, Benefit, Risk

Answer: A   

Question: 25
 
Which of the following are benefits of using PRINCE2?
1. Provides a common vocabulary for all project participants, promoting effective communication
2. Promotes regular progress meetings for senior management
3. Plans are carefully designed to meet the needs of the different levels in the project organization, improving communication and control
4. Defines a thorough but economic structure of reports

A. 1, 2, 3
B. 1, 2, 4
C. 1, 3, 4
D. 2, 3, 4

Answer: C   

http://www.certifyguide.com/exam/PRINCE2/

Vendor Name: PRINCE2
 

Exam code: PRINCE2
 

Exam Name: PRINCE2 Foundation
 

Click the link below to get full version

http://www.certifyguide.com/exam/PRINCE2/

No comments:

Post a Comment