Wednesday, 14 May 2014

PMI-SP PMI Scheduling Professional Certification

Vendor Name: PMI
 

Exam code: PMI-SP
 

Exam Name: PMI Scheduling Professional
 

Click the link below to get full version
http://www.certifyguide.com/exam/PMI-SP/

http://www.certifyguide.com/exam/PMI-SP/

Question: 1

 
Once the project's WBS has been created what process may happen next?

A. Estimate activity resources
B. Define activities
C. Estimate activity durations
D. Sequence activities

Answer: B    

Explanation:
The define activities process is the process that may begin once the project's WBS has been  completed and approved. It is possible, in some  projects, to complete the WBS and the activity list at the same  time. Answer option D is incorrect. Sequencing the activities cannot happen until the activity list has been  created.  Answer option A is incorrect. Estimating activity resources is dependent on the activity list, so this  choice is not valid.  Answer option C is incorrect. Estimate activity durations are dependent on the activity list, so this  choice is not valid.

Question: 2
 
Which of the following scheduling techniques identifies the successor activities and the predecessor   activities to assist the project manager in sequencing the project work?

A. Precedence Diagramming Method
B. Schedule network template
C. Dependency determination
D. Activity on the Node

Answer: A    

Explanation:
The Precedence Diagramming Method uses both predecessors and successors as nodes in the  project network diagram. The PDM approach is  the most common network diagram approach used.  Answer option C is incorrect. Dependency determination identifies the order of the project work.  Answer option B is incorrect. The schedule network template is a tool that uses a previous project  network diagram as a base for the current  project network diagram.  Answer option D is incorrect. Activity on the node  laces activities on circles within a network  diagram. It is an example of the precedence  diagramming method.

Question: 3
 
You are the project manager of the NHGQ project for your company. You must create and distribute  performance reports every week to your key project stakeholders. What communication technique  do you normally use to distribute reports?

A. Push technique
B. Many-to-many
C. One-to-one
D. Pull technique

Answer: A    

Explanation:
Performance reports are distributed through the push technique. This means that the project  manager distributes the reports regularly  through a mechanism, such as email.  Answer option C is incorrect. One-to-one technique describes a conversation between two people.  Answer option B is incorrect. Many-to-many technique describes a conversation between many  people.  Answer option D is incorrect. A pull technique describes the recipients of the report "pulling" the  information, such as from a Website.

Question: 4
 
Your project team is executing the project plan and things are going well. Your team has reached its  first milestone and is now in the second  phase of the project. The project stakeholders have requested that you find a method to reduce the  duration of the project. They will reward  you and your project team with a 25 percent bonus of the project costs if you can finish the project  thirty days earlier than what was already  planned. The stakeholders, however, will not approve any additional labor costs as part of the  agreement. Which approach could you use to  shorten the duration of the project?

A. Perform resource leveling for the project.
B. Crash the project schedule.
C. Fast track the project.
D. Remove things from the project scope.

Answer: C    

Explanation:
Fast tracking is a technique for compressing project schedule. In fast tracking, phases are overlapped  that would normally be done in


sequence. It is shortening the project schedule without reducing the project scope. It does not add  any additional labor but it can introduce  project risks.  Answer option D is incorrect. Removing things from the project scope can reduce the project  duration, but it will not satisfy the requirements  the stakeholders have identified.  Answer option A is incorrect. Resource leveling can actually increase the project duration.  Answer option B is incorrect. Crashing can reduce the project duration but it increases the labor  expense, something the stakeholders won't  approve.

Question: 5
 
The Define Activities process is the first process in the project time management knowledge are

a. The Define Activities process creates just three outputs as a result of decomposition, rolling wave  planning, templates, and expert judgment. Which one of the following is not an output of the Define  Activities process?

A. Activity list
B. Milestone list
C. Activity attributes
D. Project document updates

Answer: D    

Explanation:
Project document updates are not an output of the Define Activities process. Project document  updates are the outputs for estimate activity resources. Project document updates include the  following:  Activity list  Activity attributes  Resource calendars  Answer option A is incorrect. The activity list is an output of the define activities process.  Answer option C is incorrect. The activity attributes is an output of the define activities process.  Answer option B is incorrect. The milestone list is an output of the define activities process.



Question: 6
 
Examine the figure given below: 

If Activity B takes eight days to complete instead of five days as schedule, how long can you now  delay Activity H?

A. Three days
B. One day
C. Four days
D. Zero days

Answer: B    

Explanation:
Activity B is not on the critical path and it has a total of four days of float. If Activity B takes a total of  eight days, it will consume three days of  float. However, the total duration of the path ABEHJ may not exceed 26 days, as this is the total  duration for the project. Although Activity H  has a total of four days of float available, the consumption of three days of float on this path will  reduce the total float for Activity H to just one  day. If Activity H is delayed by more than one day, then the project will be late.  Answer option D is incorrect. There is one day of float still available for Activity H.  Answer options A and C are incorrect. These are not the valid answers, as there is just one day of  float available for Activity H.

Question: 7
 
You are the project manager of the GHT Project. Ben, one of your project team members, does not  understand the idea of a milestone. Which of the following best describes what a milestone is?

A. A significant point in the project
B. A goal of reaching a significant delivery of project benefits by an identified date
C. An imposed date for the project to reach a given point


D. The completion of a project activity that is crucial to project completion

Answer: A    

Explanation:
A milestone is simply a significant point or event in the project. It does not have to be assigned to a  specific date, but is usually assigned to  the completion of project phases.  A milestone is the end of a stage that marks the completion of a work package or phase, typically  mark d by a high level event such as  completion, endorsement or signing of a deliverable, document or a high level review meeting.  In addition to signaling the completion of a key deliverable, a milestone may also signify an  important decision or the derivation of a critical  piece of information, which outlines or affects the future of a project. In this sense, a milestone not  only signifies distance traveled (key stages  in a project) but also indicates direction of travel since key decisions made at milestones may alter  the route through the project plan.  To create a milestone, enter 0 (zero) in the Duration field. The task will automatically be classified as  a milestone.  Answer option C is incorrect. This is a project constraint.  Answer option B is incorrect. A project goal is an objective for time, cost, scope, and other metrics.  Answer option D is incorrect. All activities must be completed in order to complete the project work.  Activities that are not completed are  quality issues that prevent the project from completing the project scope.

Question: 8
 
You are the project manager of the GHY Project. Management wants you to create a process improvement plan for your project. Your project will be studied by management and will become a  standard for all future organizational projects based on your project's performance, approach, and  implementation of project processes. All of the following should be included in your project's  process improvement plan except for which one?

A. Process boundaries
B. Process configuration
C. Targets for improved performance
D. Identification of project risks

Answer: D    

Explanation:
Identification of the project risks is not part of the process improvement plan. Identify risks is a risk  management process, and risks are recorded in the risk register.  Answer options A, B, and C are incorrect. Process boundaries, Process configuration and Targets for  improved performance are parts of the  process improvement plan.



Question: 9
 
George is the project manager of the NHQ Project and has a budget of $778,000. The project is  scheduled to last for one year with an equal amount of work completed each quarter. The second  quarter of the project has ended and George has spent $325,000 but has only finished forty percent  of the project. Management needs a variance report for the project schedule. What value should  George report in this instance?

A. .96
B. -$77,800
C. $-34,500
D. -$13,800

Answer: B    

Explanation:
Schedule variance (SV) is a measure of schedule performance on a project. The variance notifies that  the schedule is ahead or behind what  was planned for this period in time. The schedule variance is calculated based on the following  formula:  SV = Earned Value (EV) - Planned Value (PV)  If the resulting schedule is negative, it indicates that the project is behind schedule. A value greater  than 0 shows that the project is ahead of  the planned schedule. A value of 0 indicates that the project is right on target. The earned value in  this instance is forty percent of the project  budget, $778,000, and the planned value is $398,000 because George is to be fifty percent done at  the end of the second quarter, as the  work is spread evenly across all quarters. The schedule variance is -$77,800 for the project.  Answer option A is incorrect. .96 represents the cost performance index.  Answer option C is incorrect. -$34,500 represents the project's variance at completion if the project  continues as is.  Answer option D is  incorrect. -$13,800 is the cost variance for the project.

Question: 10
 
You are the project manager of the NHQ Project. Management has set a conformance to the project  schedule for your project at 0.95. What does this term mean?

A. It means the largest schedule variance you can have is five percent.
B. It is the earned value divided by the planned value for your project.
C. It is the expectation of management to be 95 on schedule at 95 percent of the project.
D. It means you will need to earn at least 95 cents per dollar invested in the project.

Answer: A    

Explanation:

Conformance to schedule is a required adherence for the project's schedule. In this instance, the  project manager must not allow the schedule to slip more than five percent.  Answer option B is incorrect. This is the description of the schedule performance index.  Answer option D is incorrect. This is the description of the cost performance index.  Answer option C is incorrect. This is not a valid statement about the project performance.

Question: 11
 
Which one of the following estimate types is a form of expert judgment?

A. Parametric estimate
B. Analogous estimate
C. Bottom-up estimate
D. Definitive estimate

Answer: B    

Explanation:
An analogous estimate is a form of expert judgment because it relies on historical information. The  historical information, assuming that it is accurate, serves as the conduit to the expert that created  the historical information. Answer option C is incorrect. A bottom-up estimate creates an activity  duration estimate for each work package in the WBS. Answer option A is incorrect. Parametric  estimating uses a parameter, such as 10 hours per fixture installation, as a base to predict the  duration of the project. Answer option D is incorrect. A definitive estimate, also known as a bottom- up estimate, accounts for the cost of each work package.

Question: 12
 
You are the project manager of the NHA Project. This project is expected to last one year with  quarterly milestones throughout the year. Your project is supposed to be at the third milestone  today but you're likely only 60 percent complete. Your project has a BAC of $745,000 and you've  spent $440,000 of the budget-to-date. What is your schedule performance index for this project?

A. 80
B. 1.02
C. 102
D. 0.80

Answer: D    

Explanation:
The schedule performance index can be found by dividing the earned value by the planned value. In  this project, it's $447,000 divided by the $558,750 for a value of 0.80.  Schedule performance index (SPI) is the measure of schedule efficiency on a project. It is used in  trend analysis to predict future performance.  SPI is the ratio of earned value to planned value. The SPI is calculated based on the following  formula:  
SPI = Earned Value (EV) / Planned Value (PV)
If the SPI value is greater than 1, it indicates better than expected performance, whereas if the value  is less than 1, it shows poor  performance. The SPI value of 1 indicates that the project is right on target.
Answer option A is incorrect. "80" is not the same value as ".80".  Answer option B is incorrect. 1.02 is the cost performance index.  Answer option C is incorrect. 102 is not a valid calculation for this question.

Question: 13
 
Fill in the blank with an appropriate phrase.
The __________ includes a description of any collateral services required, such as performance  reporting or post-project operational  support for the procured item.  
Answer:

procurement SOW  Explanation: The procurement SOW consists of a description of some collateral services required,  such as performance reporting or post-  project operational support for the procured item. The procurement SOW is revised and refined as  required when it moves through the  procurement process until incorporated into a signed contract award.
Question: 14

Mark is the project manager of the GHQ Project. He is happily reporting that his project has a  schedule performance index of 2.12.  Management, however, does not think this is good news. What is the most likely reason why  management does not like an SPI of 2.12?

A. It is not good news because a larger number means the schedule duration estimates were  likely to be wrong to begin with.
B. They likely do not understand the SPI formula.
C. It is not good news, as the number should be closer to 100 than 0.
D. It is good news, but Mark may have large cost variances to achieve this value.

Answer: A    

Explanation:
Cost and schedule performance indexes should be as close to 1 as possible. A larger value, such as  2.12, means that the schedule duration  estimates were likely bloated or incorrect to begin with.  Answer option B is incorrect. This is not the best choice for this question.  Answer option C is incorrect. The number should not be close to 100; it should be close to 1.  Answer option D is incorrect. While Mark may have crashed the schedule and driven up costs to  achieve the SPI value, a more likely reason is  that the time estimates were bloated.

Question: 15
 
You are the project manager of the BHG Project. You are creating a network diagram as shown in the  figure:  

Mary, a project team member, reports that an identified risk is likely to happen in the project that  will affect the completion date of Activity D . She reports that the risk event will likely cause the  duration of the activity to increase by six days. If this happens what is the earliest the  project can complete?

A. 32 days
B. 29 days
C. 27 days
D. 26 days

Answer: D    

Explanation:
If Activity D increases by six days, the duration of the project will not change. There is 11 days of  float available for Activity D so it may delay by six days without affecting the project end date.  What is float?  Float or total float (TF) is the total amount of time that a schedule activity may be delayed from its  early start date without delaying the project finish date, or violating a schedule constraint. It is  calculated by using the critical path method technique and determining the difference between the  early finish dates and late finish dates. Answer options A, B, and C are incorrect. These are not valid  answers for the question.



Question: 16
 
Sam is the project manager of the NQQ project. He and the project team have completed the  stakeholder identification process for his project. What is the main output of the identify  stakeholders process?

A. Communications management plan
B. Stakeholder register
C. Requirements
D. Stakeholder management strategy

Answer: B    

Explanation: According to the PMBOK, the main output of the identify stakeholders process is the  stakeholder register. The stakeholder register is a project management document that contains a list  of the stakeholders associated with the project. It assesses  how they are involved in the project and identifies what role they play in the organization. The  information in this document can be very  perceptive and is meant for limited exchange only. It also contains relevant information about the  stakeholders, such as their requirements,  expectations, and influence on the project.  Answer option A is incorrect. The communications management plan is an output of  communications planning.  Answer option D is incorrect. The stakeholder management strategy is an output of stakeholder  identification, but it is not the main output.  Answer option C is incorrect. Requirements are not an output of the stakeholder identification  process.

Question: 17
 
You work as a project manager for BlueWell Inc. Management has asked you not to communicate  performance unless the CPI is less than 0.96  or the SPI dips below 0.98. What type of report would you create for management, if these instances  develop in your project?

A. Cost variance report
B. Exceptions report
C. Performance management report
D. Schedule variance report

Answer: B    

Explanation:
The best answer is simply an exception report.


An exception report refers and documents the major mistakes, mishaps, and goofs. In other words,  it itemizes the important and critically  significant piece of documentation that is vital to the proper and effective functioning of a project. It  does not document what has gone right,  but rather documents what has gone wrong.  Answer option C is incorrect. A performance management report is not a valid project management  report.  Answer option A is incorrect. The question is asked a out cost and schedule so this answer would  not be appropriate for both the cost and  the schedule.  Answer option D is incorrect. The question is asked about cost and schedule so this answer would  not be appropriate for both the cost and  the schedule.

Question: 18
 
You are the project manager of the HQQ Project. Your project is running late by ten percent of  where you should be at this time. Management is concerned. Considering that the project has a BAC  of $567,899, you are thirty percent complete, and you have spent $179,450. What is this  project's to-complete performance index based on the current BAC?

A. 1.02
B. 0.010
C. 0.75
D. 0.95

Answer: A    

Explanation: This project is not performing well on schedule, but moderately well on costs. The  project's TCPI based on the current BAC is 1.02. To-complete Performance Index (TCPI) is the  measured projection of the anticipated performance required to achieve either the BAC or the  EAC. TCPI indicates the future required cost efficiency needed to achieve a target EAC (Estimate At  Complete).Once approved, the EAC supersedes the BAC as the cost performance goal. Any  significant difference between TCPI and the CPI needed to meet the EAC should be accounted for by  management in their forecast of the final cost.  The formula for TCPI is as follows:  TCPI = {(BAC-EV)/(BAC-AC)}  Answer option D is incorrect. 0.95 is the project's TCPI value based on the estimate at completion.  Answer option C is incorrect. 0.75 is the project's schedule performance index.  Answer option B is incorrect. 0.010 is not a valid calculation.


Question: 19
 
Andy works as the project manager for Bluewell Inc. He is developing the schedule for the project.  There are eight tools and techniques that a project manager can use to develop the project  schedule. Which of the following is a tool and technique for the Schedule Development process?

A. Schedule compression
B. Reserve analysis
C. Variance analysis
D. Expert judgment

Answer: A    

Explanation:
Schedule compression is a tool used as part of the Schedule Development process.  The tools and techniques for schedule development are as follows:  Schedule network analysis  Critical path method  Critical chain method  Resource leveling  What-if scenario analysis  Applying leads and lags  Schedule compression  Scheduling tool  Answer options D, B, and C are incorrect. These are not tools and techniques for schedule  development.

Question: 20
 
You are the project manager for your organization. You have recorded the following duration  estimates for an activity in your project: optimistic 20, most likely 45, pessimistic 90. What time will  you record for this activity?

A. 48
B. 20o, 45m, 90p
C. 90
D. 45

Answer: A    

Explanation:
This is an example of a three-point estimate. A three-point estimate records the optimistic, most  likely, and the pessimistic duration, and then records an average for the predicted duration  Three-point estimate is a way to enhance the accuracy of activity duration estimates. This concept is  originated with the Program Evaluation and Review Technique (PERT). PERT charts the following  three estimates:



Most likely (TM): The duration of activity based on realistic factors such as resources assigned,  interruptions, etc.  Optimistic (TO): The activity duration based on the best-case scenario  Pessimistic (TP): The activity duration based on the worst-case scenario  The expected (TE) activity duration is a weighted average of these three estimates:  TE = (TO + 4TM + TP) / 6  Duration estimates based on the above equations (sometimes simple average of the three estimates  is also used) provide more accuracy. It  can be calculated as follows:  TE = ( 20 + 45*4 + 90) / 6  = 290/6  =48  Answer options B, C, and D are incorrect. These are not the valid answers for this question.

Question: 21
 
You are the project manager of the NHQ Project. You have created the project network diagram as  shown in the figure:

You are concerned about a risk on Activity G that if it happens will delay the project by four days. You would like to utilize float for Activity G . How much float is available for Activity G to help offset  the risk event?

A. Five days
B. Four days
C. Eleven days
D. Zero

Answer: D    

Explanation:
There is no float available for Activity G because it is on the critical path.  Float or total float (TF) is the total amount of time that a schedule activity may be delayed from its  early start date without delaying the project finish date, or violating a schedule constraint. It is calculated by using the critical path method technique and determining the difference between the  early finish dates and late finish dates. Answer options B, A, and C are incorrect. There is no float  available for Activity G because it is on the critical path.

Question: 22
 
Beth is the project manager for her organization. Her current project has many deliverables that  have been defined at a high level, but the details of the deliverables are still unknown. In her project,  Beth is planning in detail only the activities that are most imminent in the project work. This  approach to project management planning is known as what?

A. Imminent activity management
B. Rolling wave planning
C. Predecessor-only diagramming
D. Decomposition

Answer: B    

Explanation: Rolling wave planning is a technique to plan and do the most imminent project work  before moving onto the details that are far off in the project schedule and project plan.  Rolling wave planning is a technique for performing progressive elaboration planning where the  work to be accomplished in the near future is planned in detail at a low level of the work breakdown  structure. The work to be performed within another one or two reporting periods in the  near future is planned in detail as work is being completed during the current period.  Answer option D is incorrect. Decomposition is the process of breaking down work packages into the  activity list.  Answer options A and C are incorrect. These are not valid project management terms.

Question: 23
 
Gina is the project manager for her organization and she is working with her project team to define  the project activities. In this project, the stakeholders are sensitive to the project completion date,  so Gina is stressing to her project team members that while they need to provide and account for all  of the project activities, they should focus on one work package in the WBS at a time. In order to  start the decomposition of the project work packages into activities, Gina will need all of the  following except for which one?

A. Scope baseline
B. Organizational process assets
C. WBS
D. Enterprise environmental factors

Answer: C    

Explanation: According to the PMBOK, Gina will not need the WBS directly, but will rely on the scope  baseline.A Work Breakdown Structure (WBS) in project management is a tool that defines a project  and groups the project's discrete work elements in

a way that helps organize and define the total work scope of the project. A WBS element may be a  product, data, a service, or any  combination. WBS also provides the necessary framework for detailed cost estimating and control  along with providing guidance for schedule  development and control.  Answer option A is incorrect. The scope baseline is an input to define the project activities.  Answer option D is incorrect. Enterprise environmental factors are an input to define the project  activities. Answer option B is incorrect. Organizational process assets are an input to define the  project activities.

Question: 24
 
You have created the project network diagram for the ABC project. You are exploring total float and  free float for that project. Martin, a project team member, wants to know the difference between  total float and free float. What is the difference between total float and free float?

A. Total float is the amount of time an activity can be delayed without delaying any project  successors, whereas free float is the amount of time an activity can be delayed without  delaying the project completion date.
B. Total float is the amount of time an activity can be delayed without delaying the project  completion date, whereas free float is the amount of time an activity can be delayed without  delaying any project successors.
C. Total float is the amount of time an activity can be delayed without delaying the project  completion date, whereas free float is the amount of time an activity can be delayed without  delaying any project predecessors.
D. Total float is the amount of time a non-critical activity can be delayed without delaying any  project successors, whereas free float is the amount of time an activity can be delayed without  delaying the project completion date.

Answer: B    

Explanation: Total float is the time you can delay an activity without delaying the project end date,  whereas free float is on each activity and does not affect the early start date of successor activities.  Float, also called slack, is the amount of time an activity can be delayed without affecting any  subsequent activities. There are two types of floats available:  Free Float: It is the amount of time a schedule activity can be delayed without delaying the early  start date of any immediately  following schedule activities.  Total Float: It is the total amount of time that a schedule activity may be delayed from its early start  date without delaying the project  finish date, or violating schedule constraint.  Float is calculated by using the critical path method technique.  Answer options C, A, and D are incorrect. These are not accurate definitions of free float and total  float.



Question: 25
 
John works as a project manager of the NHQ Project. He has created the project network diagram as  shown in the figure:  
Based on the project network diagram, how much float is available for Activity H if Activity B is  delayed by four days and Activity E is delayed by two days?

A. Zero
B. One
C. Four
D. Five

Answer: A    

Explanation: The path of ABEHJ will take 22 days to complete and cannot exceed 28 days or else the  project will be late. If Activity B takes four additional  days and Activity E takes two additional days, this adds (4+2= 6) six days to the path, bringing the  path's duration to exactly (22+6 = 28)  days. There is no available float left for Activity D or H.  Float or total float (TF) is the total amount of time that a schedule activity may be delayed from its  early start date without delaying the  project fish date, or violating a schedule constraint. It is calculated by using the critical path  method technique and determining the  difference between the early finish dates and late finish dates.  Answer options B, C, and D are incorrect. There is no float available because the path's duration has  increased to 28 days.


Question: 26
 
Ben is the project manager for his organization. His project has 26 stakeholders this week and will  have five additional stakeholders next week. How many more communication channels will Ben's  project have next week?

A. 140
B. 10
C. 325
D. 5

Answer: A    

Explanation:
Ben's project will have 140 more communication channels because of the five additional  stakeholders. To solve the question, you will need to  find the current stakeholder communication channels first, which is (26*25)/2= 325, and then find  the difference of the number of channels for  the five additional stakeholders.  You can use the formula of N(N-1), where N is the number of stakeholders. In this example, the  formula would read:  Total number of communication channels that Ben will have next = ((31*30)/2)-((26*25)/2  =140  Answer option D is incorrect. Five is the number of additional stakeholders.  Answer option B is incorrect. 10 is the number of communication channels among just five  stakeholders.  Answer option C is incorrect. 325 is the number of current communication channels.



Question: 27
 
You are the project manager for your company. You are working with the activities defined in the  figure below.  
What will happen to your project if Activity F takes five additional days to complete than what was  expected?

A. Your project's critical path will shift to ACFI.
B. Your project will be late by five days.
C. Your project can still complete on time as float is available on Activity I.
D. Your project will now have two critical paths.

Answer: B    

Explanation: Activity F is on the critical path of ACFHK of 30 days. By adding five additional days to  Activity F, the project will now take 35 days to complete. Answer options C, A, and D are incorrect.  These are not the valid answers.

Question: 28
 
You are the project manager for your organization. You need the oak cabinets for your project  delivered by December 1 in order to install the floors around the oak cabinets by December 15. Your  company's procurement office generally takes 45 days to complete procurement orders. Based on this information, how should you schedule the lead time for the cabinet delivery?

A. Cabinet procurement December 1, plus 45 days lead time
B. Cabinet procurement November 15
C. Cabinet procurement December 1, minus 45 days lead time
D. Cabinet procurement December 15 minus 45 days lead time



Answer: C    

Explanation:
The cabinet procurement and delivery must be completed by December 1. By scheduling the activity  to finish on December 1 with minus 45  days lead time for procurement, the cabinets will arrive by the needed date.  Answer option A is incorrect. Lead time is always negative time, lag time is positive time. This choice  would cause the cabinets to not arrive  until 45 days after December 1.  Answer option D is incorrect. This choice would cause the cabinets to arrive on December 15 when  the floors are to be installed.  Answer option B is incorrect. This choice is not the best answer because it does not necessarily  account for holidays, weekends, or other  factors in the project calendar. By scheduling the cabinet for December 1 and working backwards  through lead time, the project's PMIS will  account for these breaks in the project work.

Question: 29
 
Your project has a BAC of $750,000 and is 75 percent complete. According to your plan, however,  your project should actually be 80 percent complete. You have spent $575,000 of your project  budget to reach this point and you are worried about the project not being able to complete based  on your current project budget. What is the to-complete performance index for this project?

A. 0.98
B. -$16,677
C. 1.07
D. 0.94

Answer: C    

Explanation:
The to-complete performance index can be found by using the formula (BAC-EV)/(BAC-AC) for a  value of 1.07. The higher the value is from 1, the less likely the project will meet the BAC.  To-complete Performance Index (TCPI) is the measured projection of the anticipated performance  required to achieve either the BAC or the  EAC. TCPI indicates the future required cost efficiency needed to achieve a target EAC (Estimate At  Complete).Once approved, the EAC  supersedes the BAC as the cost performance goal. Any significant difference between TCPI and the  CPI needed to meet the EAC should be  accounted for by management in their forecast of the final cost.  The formula for TCPI is as follows:  TCPI = {(BAC-EV)/(BAC-AC)}  Answer option A is incorrect. 0.98 is the project's cost performance index.  Answer option D is incorrect. This is the project's schedule performance index.  Answer option B is incorrect. -$16,667 is the project's variance at completion.



Question: 30
 
You are the project manager of the NHT Project. This project has 12,345 office doors to install  throughout a campus. Each of the doors costs the project $456 and requires special hardware to  electronically lock and open the doors. You've gathered the project team before they begin  the installation for a hands-on training. As a group you and the project team install 50 doors  following a checklist of instructions so that every door will be installed exactly the same throughout  the campus and with minimal waste. This is an example of what project execution technique?

A. Preventive action
B. Defect repair validation
C. Implemented corrective action
D. Quality control

Answer: A    

Explanation: This is an example of a preventive action as you're working with the team before they  install the doors to train them on the installation. The checklist is a quality control tool but the  question was asking for a project execution activity. Preventive and corrective actions are part of  project execution.  Answer option D is incorrect. Quality control is a controlling and monitoring process, not an  executing process.  Answer option B is incorrect. The defect repair validation comes after the project team has corrected  an error - something that has not  occurred in this instance.  Answer option C is incorrect. Corrective action is a response to something that needs to be corrected  in the project.




http://www.certifyguide.com/exam/PMI-SP/

Vendor Name: PMI
 

Exam code: PMI-SP
 

Exam Name: PMI Scheduling Professional
 

Click the link below to get full version

http://www.certifyguide.com/exam/PMI-SP/

No comments:

Post a Comment